Designing the connection between a steel building and its foundations

Sandwich panels

In brief

The connection between a steel hall and its foundation requires calculation of the entire node. Anchors, base plate, concrete, grout and the method of transferring forces are selected. A chemical anchor is one of the available solutions, but it does not suit every hall automatically. The bar diameter and hole depth should not be chosen on the basis of the building’s mass or general advice. The entire connection system is checked. The base transfers vertical and horizontal forces as well as moments resulting from the structure’s behaviour. Wind can cause part of the connection to be lifted, even though the entire hall is heavy. Loads depend on the frame layout, bracing and location conditions. Therefore the number of anchors does not simply follow from the size of the base plate.

Lower part of a hall façade made of sandwich panels at a concrete plinth

What forces act at the column base?

The base plate transfers vertical and horizontal forces as well as moments arising from the behaviour of the structure. Wind can cause part of the connection to lift, even though the entire hall is heavy. The loads depend on the frame layout, the bracing and the location conditions. The number of anchors therefore does not simply follow from the size of the base plate. Reactions from the structural analysis are required.

The design determines how shear forces are transferred to the foundation. Various components of the joint may participate in this. One mechanism should not be assumed without verification. The stiffness of the plate, the arrangement of the bars and the contact with the grout are also important. An incidental substitution of a component can change the behaviour of the entire connection, even if the new bar has the same diameter.

Will a bonded anchor always be suitable?

Bonded anchors are used after the concrete has been placed, within the scope defined in the documentation for the given system. In a new hall, cast-in anchors can also be provided during concreting. The choice depends on the design, the sequence of works and the ground conditions. There is no rule that resin provides a better fixing in every foundation. The specific solution is assessed.

The bonded system comprises the mortar, a suitable steel element and a defined installation method. Check the scope of the approval, including cracked concrete, moisture conditions and temperature. The documentation may specify various drilling and cleaning methods. A bar, resin and instructions from different systems must not be combined arbitrarily. A similar-looking cartridge alone does not prove conformity.

What needs to be checked in an existing foundation?

Data on the concrete, dimensions and reinforcement are required. Distances from the edge, anchor spacings and the thickness of the element are important. A foundation that is too small can limit the load-bearing capacity of the entire group. A deeper hole does not always solve the problem. Near the edge, possible concrete failure must be taken into account, not only the strength of the steel bar.

Before drilling, the position of the reinforcement and installations is determined. Do not cut structural bars merely to fit the hole in a convenient place. If the actual foundation differs from the documentation, an assessment by the designer is required. The same applies to cracks, voids and previous holes. The substrate must be investigated before ordering the final fixing layout.

Steel-framed buildings – SteelProfil range and free quote

Why does hole preparation matter so much?

The diameter and depth of the hole must correspond to the documentation of the selected system. Dust or loose material can impair the adhesion of the mortar to the substrate. The specified cleaning procedure and suitable accessories are used. We do not state a single number of blow-outs for all anchors, because the requirements depend on the solution and the drilling method.

When introducing the mortar, the conditions specified by the manufacturer must be observed. These include preparation of the cartridge, the filling method and the time allowed for seating the rod. Working conditions are assessed in the concrete, not merely on the air thermometer. Mortar in a heated foundation may behave differently from mortar in a cool one. A wet hole is permissible only within the appropriate system and range.

When can the fixing be loaded?

The curing time depends on the product and the substrate temperature. Do not assume that every anchor is ready after an hour. During this period the connection must not be loaded in any way not provided for in the instructions. A distinction must be made between the time allowing the rod to be seated and the time after which further operations may begin. Both conditions affect the organisation of the works.

After the structure has been erected, the specified grouting, adjustment and tightening are carried out. The tightening torque should not result from the force applied by the operator of the wrench. The sequence of assembling the frames and the temporary securing of stability are also important. An anchored column without proper erection support does not yet mean a stable hall. The erection plan must take into account the entire stage of assembling the structure.

How should the acceptance of connections be prepared?

Keep the design of the node, the identification of the anchors and mortars, and the installation information. Records of temperature, dates of execution and the time of commencement of loading are useful. The inspection should confirm compliance with the design, and not merely that all nuts are tightened. The scope of any testing is determined for the given fixing and the given structure.

If an anchor has been installed in the wrong place or the hole is incorrect, do not remedy the situation at random. An agreed repair method is required. For the client, one thing matters most: they are buying a complete, designed connection, not just the resin itself. Correct anchoring protects the structure and allows the loads from the cladding, the roof and the use of the hall to be safely transferred to the foundation.

7 branches. Materials closer to your project.

Izoprofil.eu map of seven branches offering sandwich panels, PIR boards and sheet metal
  • SEROCK — Dzierżenin 34 E [mapa]
  • BŁONIE — ul. Sochaczewska 138A [mapa]
  • RADOM — ul. Grobickiego 8 [mapa]
  • ŁÓDŹ — Natolin 8 [mapa]
  • OLSZTYN — Barczewo, ul. Prosta 9 [mapa]
  • WROCŁAW — ul. Jerzmanowska 10C [mapa]
  • GORZÓW WLKP. — ul. Zielona 33/34 [mapa]

Check prices and availability: +48 500 409 109

Free quote

Materials for your project