The design for above-rafter insulation with IDELCO α-therm SARKING must first establish how much space for board thickness the specific roof structure provides and how the fixing will engage the rafters. The board data do not automatically specify the screw spacing. IDELCO α-therm SARKING is a PIR board for pitched roofs with a multi-layer aluminium laminate on both faces and a tongue-and-groove profile on all four sides. In the design it is specified as the layer above the rafters, with a separate preliminary covering selected to suit the solution. The functional description should distinguish the board’s laminate from the preliminary covering membrane and replace the terms “polyurethane boards” and “polyurethane foam” with the precise designation of the PIR product. The drawings cover the preliminary covering and the junctions with the rest of the building’s insulation.

In this article
α-therm SARKING PIR boards above the rafters
The product name alone does not describe the solution: the board does not contain a factory-made membrane with laps. The aim is to establish the full cross-section protecting the structure and the interior against precipitation. The documentation must specify the list of layers above and below the board, how they are terminated at the eaves, and where they are to be used.
Continuity of the layer and the influence of joints
The α-therm SARKING layer with a thermal conductivity of 0.022 W/(m·K) is described in the calculation as insulation running above the timber. As a result, there is no such interruption in this layer across the width of the rafter as there is with insulation placed solely between the elements. The thermal schedule should correspond to this arrangement in cross-section.
For the adopted SARKING board from the 100–160 mm range, a detail drawing of the wall-to-roof junction is required. The assessment of heat flow at the junction and at the fixings should be based on it. Moving the insulation above the timber does not automatically eliminate the thermal bridges arising from the spatial geometry of these locations.
Large-format polyurethane insulation
The SARKING boards have a format of 1200 × 2400 mm, so they need stable support during handling and cutting. Successive boards must be joined so that the profile is matched along the entire length. The construction design must show the large SARKING format of 1200 × 2400 mm with a profile on all four sides.
The working drawing should help prepare transport and a cutting station for the large SARKING boards. It is not worth leaving this to the crew at the last moment, since incorrect handling can damage the long edge needed for fitting. The adopted geometry is to allow repeatable fields to be laid without accidentally increasing the number of cut pieces. For works inspection, specify the laying direction, the run of the supports and the condition of the tongue and groove. Also set out the inspection before covering.
New roof slope height and water drainage
An above-rafter system raises the level of the roof slope, which changes the roof height at the eaves, ridge and junctions with flashings. Check this before ordering material. In the analysis of the building component’s conditions, include the new roof slope height after adding SARKING above the existing structure.
Adapt the gutter, flashings and the space under the covering to the new SARKING level. The model and detail must take into account that the added insulation shifts the position of the terminations, even when the interior of the attic remains unchanged. The material set is to ensure continuous water drainage and the operating conditions of the covering. In the specification, describe the height balance at the eaves, ridge and roof window installation, with separate functions for the protective layers.
Fixing and requirements in the vicinity of the chimney
The declared compressive stress of α-therm SARKING is at least 150 kPa at 10% deformation, and the reaction-to-fire class is F. The CS parameter of at least 150 kPa describes the behaviour of the core under load, whereas reaction F concerns the product’s contribution to fire and does not make it non-combustible. Service requirements should therefore be formulated separately for CS and for the reaction to fire of SARKING, without drawing conclusions about arbitrary spans from these figures.
When assessing conformity, the SARKING properties refer to the loads and requirements of the entire roof, and not only to the board itself. The core parameters do not confirm any arbitrary span or the butting of PIR against a hot chimney. The design data should allow the structure and protective details to be selected within the intended scope of application; when approving the product, check the fixing pattern, the support conditions and the solution for the vicinity of the chimney flue, as well as conformity with the design.
Insulation with polyurethane: the cost of a complicated roof slope
The bill of quantities for SARKING should relate the number of boards to the actual plan projection: roof valleys, dormers, windows and other penetrations through the roof slope. The surface area alone does not describe the work at the edges. The scope of the order therefore also includes the necessary accessories and edge finishing, and the pricing must take these roof elements into account.
In the material procedure, include offcuts and accessories beyond the basic SARKING area. Two roofs with the same number of square metres may require different amounts of work at the edges. The procedure should allow the cost of the completed thermal insulation with a correctly finished covering to be compared; when agreeing the delivery, specify a separate bill of quantities for the fields, openings, edges and the necessary fixings.
A case worth considering
In the α-therm SARKING design, the board thickness within the range of 100–160 mm and the fixing method must be specified. The availability of these thicknesses alone does not determine the fastener spacing — this results from the roof geometry and the structural data. The drawings should also show the membrane terminations, and the material specification and the construction detail complement each other.