In the specification of a flat roof with a low rooflight upstand, where little space remains for the new layers, state the PIR board and its delivery variant unambiguously. Kingspan Therma TR26 has a PIR core and a multilayer facing containing aluminium on both sides; the format, thickness and edge type affect the layout and coverage. The Polish catalogue describes roofs on a concrete, steel or timber substrate, with covering that is mechanically fixed or ballasted. Bring the board up to the vertical rooflight wall without a break in the insulation, and record the adopted variant in the documentation. Keep the requirements for the board separate from the assessment of the complete roof.

In this article
Unambiguous identification of the product
A shortened record of the name alone is not sufficient, because merely increasing the thickness on the open roof slope will not resolve the termination at an obstacle. The functional assumptions are to allow the required thermal effect to be maintained and correctly executed flashings around the rooflight to be accommodated. In the design documentation, state the upstand height, the covering level and the method of connecting the horizontal insulation to the vertical part, together with a reference to the relevant section.
Assumptions for the calculations
The declared lambda of Therma TR26 is 0.022 W/(m·K). For a thickness of 100 mm the catalogue states RD 4.50 m²K/W, and for 140 mm — 6.35 m²K/W. In the comparison of polyurethane boards in the calculations, assign the value RD 4.50 m²K/W to Therma TR26 with a thickness of 100 mm.
RD for TR26 describes the material itself, whereas the U-value is calculated for the complete roof covering — each value must be linked to the correct version of the calculation. The reciprocal of RD does not take into account the other layers or the joints of a real roof, which is why the parameter remains tied to the declared scope. In the design, retain the RD of the selected variant as well as the influence of the fixing and the geometry of the terminations.
Material requirements and inspection of execution
For Therma TR26 the Polish catalogue states at least 120 kPa at 10% deformation and reaction to fire E. The compression of the board is not a permissible permanent load for the entire roof. In the table of mechanical and fire requirements, highlight the ballasted system in which the weight of the load-distribution layer relates to the entire structure.
The weight and pressures in a system with TR26 must be transferred through the appropriate layers to the structure, so that the product document does not replace the required assessment of the application. Evidence for one case cannot be extended arbitrarily, because CS120 alone does not define the permissible ballast or the weight of roof-mounted equipment. The product and application documents are meant to allow the load-transfer arrangement to be selected without equating the stiffness of the board with the load-bearing capacity of the roof covering. When approving the material, compare the set of permanent loads, local pressures and the scope of the fire assessment of the adopted roof configuration with the actual configuration of the building envelope.
In the TR26 specification, the format must be linked to the thickness and edge profile: the catalogue stipulates that the 1200 × 600 mm format does not apply to the 85 mm variant. This detail affects cutting and delivery. The external dimension must be distinguished from the usable one, because describing it only by nominal area makes it difficult to compare a quantity take-off with the actual layout of the laid boards.
Separate technical requirements
In the detail of the roof penetration with TR26, the passage through the laminate and through separate protective layers must be shown. The aluminium surface of the board does not seal the joints at the installation, rooflight or parapet. The design must therefore resolve water protection and vapour flow control independently, instead of assigning these tasks to the facing alone.
The laminate and the sealing layers must be connected to the sealing of the specific roof duct in accordance with the thermal and moisture conditions adopted for the building element. The polyurethane foam alone does not complete the analysis, because the silver facing does not seal the gap between the product and the installation. In the specification, indicate the turn-up of the covering, the run of the vapour control layer and the closing of the opening perimeter, as well as the limits of responsibility of the individual layers.
Description of the connections in the design
Therma TR26 is available in the formats 1200 × 600 and 1200 × 2400 mm, with square edges or with a rebated edge. The 1200 × 600 mm format does not include the 85 mm thickness given in the catalogue. On the construction drawing, indicate the arrangement of the boards of both formats on the roof slope with several rooflights.
The TR26 board layout results from the ordered edge and the actual support at the openings; transfer the verification of this layout to the construction drawing. Changing the format changes the number of cut pieces and the pattern of joints around the openings, so do not leave this choice to the installers. The geometry should provide supported connections without accidental short sections at the base of the rooflight. When accepting the polyurethane insulation, check the delivery format, the edge variant and the conformity of the row plan with the roof substrate.
Principles for assessing equivalence
In the Therma TR26 order, state the thickness, format and type of edge. Fixing and covering scope are part of the complete roof solution. When assessing the “polyurethane insulation” item in the bill of quantities, compare the TR26 offer in terms of thickness, coverage and the method of fixing the layers.
Price the fasteners and flashings together with the insulation of the main field, and keep the criteria agreed for the equivalent in the tender evaluation. Conformity of a single characteristic is not enough when mechanical fixing and ballasting differ across several material items. Compare roof variants with the same function and an identical scope of completed works. In the conformity report, enter the number of boards by coverage, the protective materials and the bill of works for the rooflights and edges.